Paving the way …

Construction crews are paving the way to completion on the SR-101/Peavine Rd. expansion project. TDOT reports that the projected completion is by the end of May. The November 2020 completion date was adjusted at the contractor’s request because of underground utilities that were not shown on the project plans. The extension was granted the completion date was moved to February 2021. However, because the adjusted completion date was set for the winter, the contractor had to wait until spring to put final paving on the project due to TDOT’s seasonal paving limitations.